How much does a knockdown rebuild cost?
A typical knockdown rebuild with a 220 m² single-storey home costs about $672,000 to $943,000 in 2026, before land. The new build is the biggest part, but demolition, asbestos, services, approvals and rent while you are out add $100,000 or more. Enter your own size and rent below for an itemised estimate.
Knockdown rebuild estimate
Likely total: $672,000 to $943,000, typical around $792,000, excluding land.
| Item | Low | Typical | High |
|---|---|---|---|
| Build: 220 m² at $2,400 to $2,900 per m² | $528,000 | $583,000 | $638,000 |
| Demolition and site clearing | $15,000 | $27,000 | $40,000 |
| Asbestos survey and removal (bonded) | $4,000 | $9,000 | $14,000 |
| Disconnect and relocate services | $4,000 | $10,000 | $22,000 |
| Design, engineering and approvals | $12,000 | $25,000 | $45,000 |
| Soil test, site fencing, temporary power, driveway crossover | $9,000 | $14,000 | $22,000 |
| Landscaping, driveway and fencing | $18,000 | $35,000 | $65,000 |
| Rent while you are out: 40 weeks at $650 | $26,000 | $26,000 | $26,000 |
| Moving out and back in | $3,000 | $5,000 | $7,000 |
| Contingency (10% of the build) | $53,000 | $58,000 | $64,000 |
| Total | $672,000 | $792,000 | $943,000 |
What people actually paid in New South Wales
New houses built in NSW in 2024-25 averaged $2,396 per m² (ABS data). Brought forward with the ABS house price index (5.2% in the year to September 2026), that is about $2,520 per m². These averages are mostly volume-builder homes, and contracts signed a year or two earlier, so current quotes usually sit above them.
Sources: Draftee: knock down rebuild cost 2026 (5 October 2026); ABS-based state averages; ABS price index. How we calculate.
How a knockdown rebuild works
- 1
Check the block
Confirm zoning, overlays (heritage, bushfire, flood), easements and any sewer main on the block. A heritage overlay can rule out demolition altogether.
- 2
Choose a design and builder
Pick a plan that suits the block width and orientation, and get fixed-price quotes that list what is excluded.
- 3
Get approvals
Demolition and the new home are approved together through a CDC, DA or building permit, depending on your state and site.
- 4
Move out and disconnect
Services are disconnected and abolished before demolition. Plan rent, storage and moving for the whole build.
- 5
Demolish and clear
Asbestos is removed by a licensed removalist first, then the house is demolished and the site cleared.
- 6
Build and hand over
Slab, frame, lock-up, fit-out, then final inspection and occupancy certificate before you move back in.
Common questions
How much does a knockdown rebuild cost?
A knockdown rebuild with a 220 m² single-storey project home comes to about $672,000 to $943,000, typical around $792,000, including demolition, asbestos removal, disconnecting services, design and approvals, site setup, landscaping, 40 weeks of rent and a 10% contingency on the build. A 280 m² double-storey rebuild is about $984,000 to $1,289,000.
How much does demolition cost?
Demolishing a single-storey house and clearing the site usually costs $15,000 to $40,000. Asbestos is extra: a survey and bonded asbestos removal add about $4,000 to $14,000, and friable asbestos can cost $15,000 to $40,000.
Is a knockdown rebuild cheaper than renovating?
Often not cheaper, but often better value. A common rule of thumb is that once a renovation would cost more than about 50 to 60% of rebuilding, a knockdown rebuild usually makes more sense, because you get a new home with fewer unknowns. Use the calculator's renovation field to compare a real quote.
What costs do people forget in a knockdown rebuild?
Rent while you are out (40 weeks at $650 a week is $26,000), moving twice, storage, disconnecting and relocating services ($4,000 to $22,000), and landscaping, driveway and fencing ($18,000 to $65,000), which build contracts often leave out.
Do I need approval to knock down my house?
Yes. Demolition needs approval, usually as part of the approval for the new home: a CDC or DA in NSW, a building permit (and sometimes a planning permit) in Victoria, and building approval in Queensland. Heritage overlays can stop demolition.
Building on a vacant block instead? Use the house build cost calculator, or browse house plans by block width.